Projects

Projects


a conveyor belt is silhouetted against a blue sky in a factory
By K and R Fabrications 29 Jun, 2023
The overall objective of the West Cliff Coal Preparation Plant Raw Coal and Reliability Improvement Project (RC&RIP) is to replace thirty year old process elements and increase the reliability of the operating plant to meet operational demands. The project involved upgrading the existing plant through implementation of carefully planned additional structures and replacing dated process elements. This particular project involved all supply, fabrication and erection of all steelwork for the Westcliff Coal Preparation Plant to replace all the 1-47 Coal Distribution stackout conveyor trestle legs.
an aerial view of a factory with smoke coming out of the chimneys
By K and R Fabrications 29 Jun, 2023
K&R Fabrications was the first contracting company in Australia to change a Blast Furnace Stave over the top of the bath of molten iron and coke in January 2014.  Working closely with Bluescope Steel on exchanging ideas to complete the job in the most timely but safest way possible. the scope. K&R prepared all of the new staves as well as developed and executed some of the crew training. The work was done over five one week shutdowns with eight staves changed in the first shutdown and 46 staves changed in the last. K&R Fabrication had a crew of up to 224 people on the project – whilst still crewing up for key customers outside the blast furnace project. During the August 2014 shutdown there were high winds and heavy horizontal driven rain. The normal method of using a large mobile crane to lift staves up and down could not be used. K&R successfully implemented BlueScope’s plan to use trolleys, monorails, a winch system and the personnel lift to get the staves up and down. Client representatives made the comment that they had never before seen people continue to work as our crews did in such poor weather conditions. K&R’s Furnace Top crew continued to work in the driving rain whilst soaked to the skin for their full 12 hour shift. The # 5 Blast Furnace Stave exchange project involved removing the worn out staves (water cooled copper blocks) from inside the hot furnace and replacing them with new ones above the bath of molten iron and coke. The job is unique in Australia and involves the staves being lowered in through the furnace top on winches and then being transferred to supporting wire ropes to allow them to swing close to their point of installation. The crews then use long gaffs poked through the furnace shell to capture small wire ropes attached to the staves. These ropes are pulled through the shell and allow the stave to be winched to position. Project unique characteristics include: High level concise radio communication was required as crews were in three different areas and couldn’t see each other but coordinated the lifting and positioning of the staves. Specialised training to achieve the gaffing, pushing and winching home of the staves. Extremely hot, humid and confined working space where the gaffing, gouging, bolting and welding activities take place. Subtle differences from one stave to the next which complicates the work. High quality welding is required because the 55mm thick shell of the furnace is a pressure vessel. K&R deve loped scale models for training and – together with BlueScope – set up a full scale t K&R developed several major initiatives during this project including developing scale models for training and – together with BlueScope – set up a full scale training plant which used two mobile cranes, a trial stave and a full sized segment of furnace shell. We were extremely fortunate to have a client who appreciated the significant gains from these initiatives and was happy to let us develop them. K&R assisted BlueScope with many technical changes and engineering improvements during the project. This included a strong collaborative effort to work out the best removal and installation sequences.
Omya conveyor removal
By K and R Fabrications 29 Jun, 2023
Omya is a global producer of calcium carbonate with 175 plants in over 50 countries. Omya Australasia operates 4 quarries and 5 mineral processing plants in Australia and New Zealand to extract, process and supply Calcium Carbonate to a wide range of applications and customers. The Moss Vale operation in the NSW Southern Highlands operates a range of mineral processing equipment to supply various construction and agriculture markets throughout NSW. The stockpile conveyor was previously used to unload raw material feed from rail operations. With the cessation of rail deliveries, and aging structure, K&R Fabrications project scope was to remove the Stockpile Conveyor from the Moss Vale Site and relocate to an unused location onsite for dismantle. The project took three weeks to complete, and involved prework, isolations, careful alignment of the Crane for removal and cleanup onsite.
K&R Fabrication logo

At K&R our core business and core competency is heavy industry maintenance contracting. We assist industries in increasing efficiency and effectiveness of operations by providing unique full production support services and fabrication technology, helping them to be at their competitive best.

Get In Touch

Find out how K&R Fabrications can help you with your next project.

Share by: